Appendix E
Purchase Power
No. Copies Required, Including Original |
The original and twelve (12) copies of the report, as required in RP 25, shall be filed with the Commission, which report shall include the following information: |
13 | 1. The name and address of the seller(s). |
13 | 2. The identity of the generating unit(s) out of which the capacity will be delivered, if a specific unit is designated. |
13 | 3. The terms and conditions of the purchase. |
13 | 4. The portions of the purchase cost which shall be designated as capacity related and energy related. |
13 | 5. A statement with supporting documentation as to why the purchase is in the best interest of the utility and its retail customers. |
13 | 6. The rate of return sought. |
13 | 7. An effective date, not less than thirty (30) days after the date that the utility files its report. |